Tree permits before you build in Toronto, Markham, Richmond Hill and Vaughan

Which trees are protected in each GTA municipality, how tree protection zones affect additions and custom homes, and how to plan around them early.

Residential street lined with mature trees

Trees decide more GTA construction projects than most homeowners expect. A protected tree on your lot, or your neighbour’s, can move a footprint, change a foundation, reroute a driveway or add months to a permit. Every municipality in the region protects private trees above a certain size, and the thresholds are different.

The thresholds

Municipality Private trees protected from Notes
Toronto 30 cm diameter City-owned trees of any size are protected, and trees of any size in ravine-protected areas.
Markham 20 cm diameter Tree Preservation By-law 2023-164.
Vaughan 20 cm diameter Tree Protection By-law 052-2018, including multi-stem trees with a combined 20 cm.
Richmond Hill 15 cm diameter The current by-law lowered the threshold from 20 cm, which many older guides still quote.

Diameter is measured at about chest height, 1.37 to 1.4 m above the ground depending on the by-law.

Tree protection zone sign on hoarding around a tree
Protected trees are fenced off before any work begins on site.

It isn’t only about cutting trees down

The by-laws protect trees from injury, not just removal. Excavating for a foundation, an addition or a garden suite inside a tree’s root zone can count as injury. Trenching for new services, compacting soil with equipment and storing materials under the canopy can all damage roots.

That’s why tree protection usually starts with a tree protection zone: an area around the tree, sized by its diameter, fenced off with hoarding for the whole project. Nothing is stored, driven or dug inside it without approval.

How it affects projects

  • Custom homes. The new footprint may need to stay out of a tree protection zone. Sometimes that changes the design; sometimes the foundation is redesigned to bridge roots.
  • Additions. A rear addition is often the project most affected, because the yard is where mature trees are.
  • Garden and laneway suites. Many rear yards are small, and a single mature tree can make a suite impossible or force a smaller footprint.
  • Neighbours’ trees. A tree that straddles the property line, or whose roots extend onto your lot, is protected too, and the neighbour may need to consent.

The process, in general terms

  1. Survey the trees. Locate and measure trees on the lot and within a few metres of it.
  2. Arborist report. For construction projects, an arborist assesses each tree and recommends protection or removal.
  3. Apply. Submit the permit application, the report and the site plan. Fees and replacement planting requirements vary.
  4. Install protection before any work starts, and keep it in place until the end.

Markham, for example, states that it reviews tree permit applications within 45 days of payment. Build that into the schedule.

Plan it early

The most expensive time to discover a protected tree is after the drawings are done. The cheapest is during feasibility, before the design is set. On our projects, a tree survey is one of the first things we look at.

Read more in our guides to renovating, adding on, or rebuilding and laneway and garden suite costs.